Generator Feeder Cable Replacement

Project Class: Cable Infrastructure

Project Reference: GSA/Bolling Air Force Base

Project Description: Puente CostCon JV, LLC was the prime contractor for the replacement of electrical cables from an emergency generator to the ATS (Automated Transfer Switch) in the electrical room of a secure facility. Major tasks included trenching, installing conduit (inside and outside), building the duct bank, pulling cable, terminating, testing and cutover.

Project Scope: Services included: survey, concrete and electrical work, daily safety & QA/QC checks, and providing equipment, labor and materials. Additional administration services: review of shop drawings and redlining, interpretation of construction documents, regular progress meetings, reports and safety/quality implementation, and labor relation compliance and certified payroll.